May 2022 – Pre-application Request
The Council has provided Kronos Solar with indications regarding the important impacts that the project may have on the environment and that we have to take into account for our application.
July 2022 – Screening Opinion Request
Kronos Solar has consulted the Council regarding the need for a full Environmental Impact Assessment (EIA). The Council has confirmed that no EIA is required.
August 2022 – First Draft of Design
A first proposal was designed together with qualified landscape architects, ecologists, archaeologists and other relevant specialists. This is a first draft which will be subject to your opinions and for the Council’s consideration.
September 2022 – Public Consultation Event
At the public consultation we hope to welcome you in order to answer any questions you may have as well as take into consideration your suggestions regarding the proposed project.
December 2022 – Drop-In Consultation
A drop in session hosted at Newbiggin Village Hall to provide information on the amended layout and answer any questions.
Winter 2024 – Formal Planning Application Submission
After receiving your comments and reviewing them, we aim to have all our documentation ready to submit a planning application for the proposed solar park.
Autumn 2024 – Planning Permission
The Council will validate the project and the plan will be open to public inspection during the statutory judicial review period. If there are no further changes proposed, the municipality will issue its decision, after which, the permit will be granted.
Winter 2025 – Construction
As soon as the financing is complete and all contracts with suppliers have been concluded, the construction phase can begin. The construction of the solar park will take approximately three months. During these months, various construction stages will be completed. These include the cabling, the installation of the fences, the placement of the modules, the connection of the substation and the installation of security measures.
Summer 2025 – Beginning of Operations
Once the solar farm has been constructed, the operational phase begins. The sustainably generated electricity is supplied to customers via the public electricity grid. Kronos Solar will have the ecological management carried out professionally by a (local) professional organisation. Faults will be resolved as quickly as possible and the farm will be maintained when necessary.
Summer 2060 – Decommissioning
After 35 years, the solar park will be dismantled and the plots will be delivered in their original state. The dismantling of the solar park will be carried out by an organisation that focuses entirely on the sustainable dismantling and recycling of solar panels